All projects below should be initiated by filling out the Web Request Form.

Below is information about the length of time it takes to complete work requested:

  • E-Newsletter Template — 3-4 weeks
  • Custom Graphic — 3 weeks
  • URL Redirect — 1-2 weeks
  • Custom Domain Purchase — 1-2 weeks
  • Form Edits — 1-2 weeks
  • Basic Form — 2-3 weeks
  • Interactive Form — 8 weeks
  • Custom Programming — 6+ weeks
  • Blog — 4 weeks
  • Social Media Post — 1-2 days
  • Promotional Landing Page — 3 weeks
  • Strategy — 1-3 weeks
  • Training — 1 day (1-2 weeks lead time)
  • Troubleshooting — 1-2 weeks
  • Website Edits — 3-5 days
  • New department sub-site on existing website — 3-4 weeks
  • New standalone website or major website redesign —
    This will take months and requires advanced scheduling and planning, as well as administration approval. Please contact us to find out how to get into our queue of major website projects.